Dimensions and Location
The boiler should be installed in a dry indoor location where there is sufficent space to accomodate the boiler and provide the clearances needed for maintainance.

Clearance required for 150/225 boilers in cascade system
For ease of installation,commissioning,servicing and mantainance the following clearances should be observed
- Above the boilers 750mm minimum
- Beside the boilers 500mm minimum
- Between the boilers 500mm minimum
- In front of the boilers 1000mm minimum
- Behind the boilers 1000mm minimum